That’s right, we have a slab! wahooooooooooooooo!!!! *party*
But wait!” I hear you all cry; how did all this happen?!

Rewind to November 2011: We paid deposits on land and building tender.
Fast forward to 24th March 2013 and on a random visit to our lot we see it has been cut/filled

Cut/fill

Cut/fill Fun :D

 

 

 

Then we received a call on the 25th March to say ‘Hey, we’re starting your piering today. Feel free to come check it out around lunch time.” And sure enough lunch time rolled around, we zoomed away on our lunch break to find:
Waffle pod
Look at that lovely peiring. (We assume it’s lovely!)

Then as we were celebrating Easter and thanking God for all His blessing and provision we decided to visit the lot again, just because we could.. And what a lovely thing we found:
Waffle pod
Our waffle pod!! What is a waffle pod you ask? The Waffle Pod Slab Systems allows a more accurate specification of concrete quantities, reduces waste and provides a substantial boost to building site efficiency.
It has minimal impact on the environment – there is less soil disturbance, and no excavated rubble from trenches to dispose of. (if only the polystyrene was bio-degradable!) The pods allow air pockets in the slab to form an insulating layer between the structure and the ground.

What great progess they had been making, and so quickly too!!! We went back to work (grumpily) on Tuesday only to receive an invoice in the late afternoon for our slab. Now this is the first big progress payment for us (other than all the $$$$$ we had paid up to this point) and there was no way were going to pay 20% of our total house cost without checking out that slab. Our Site Supervisor (SS) had called hubby on the previous Thursday to tell him the slab would be done on Friday the 5th of April so we weren’t expecting this invoice so soon. To our great delight we found this upon our late night arrival after work:

Slab

Cuties

 

So we’re just enjoying the quick progress while we can. Now we’ve paid Clarendon a bunch of monies I wouldn’t be surprised if things slow down a little bit. Well, that and the fact is has rained both days after the slab was poured and is forecast to rain for the next week and a half! Oh well, it just gives the slab time to cure.

Hopefully I’ll be able to share pictures of the framing and bricks as they go up over the next month or so. At this point we’re estimating we’ll be in around November (worst case) with a possibility of being in late August/early September if everything goes perfectly and promptly!

Advertisements

3 responses to “Slab kebab!

  1. melissasavage says:

    Keeping everything crossed for a speedy build and a quick moving-in!! Mwah!

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: